ST. LOUIS - The Missouri Department of Transportation has scheduled the following for Tuesday, October 7, weather permitting.
St. Louis City
I-70:
- From 9 a.m. to 3 p.m. Tuesday the right lane on eastbound I-70 from Walnut St. to I-64 will be closed for paving work.
Hampton Ave.:
- Hampton Ave. at I-64 is closed for bridge demolition work. The closure will remain in place until May 2009.
Kingshighway Blvd.:
- From 7 a.m. to 3 p.m. Tuesday and Wednesday the left lane on southbound Kingshighway Blvd. from Hospital Plaza to I-64 will be closed for paving work.
St. Louis County
I-44:
- From 9 a.m. to 3 p.m. Tuesday the right lane on westbound I-44 from Yarnell Rd. to Bowles Ave. will be closed for maintenance work.
I-64:
- Eastbound and westbound I-64 between Ballas Rd. and I-170 is closed for construction work. The closure will be in place until early 2009.
- The exit ramp from eastbound I-64 to Bellevue Ave. is closed for bridge construction work. The ramp will be closed until late 2009.
I-170:
- The ramp from southbound I-170 to westbound I-64 is closed for paving work. The ramp will be closed until early 2009.
- The center lane on northbound I-170 from Eager Rd. to Brentwood Blvd. is closed for paving work. The lane restriction will be in place until late 2009.
- The right lane on southbound I-170 from Clayton Blvd. to I-64 is closed due to construction work. The lane restriction will be in place until late 2009.
US 67:
- From 6 p.m. Monday to 6 a.m. Tuesday the right lane on northbound US 67 at I-64 will be closed for paving work.
- From 7 p.m. to 6 a.m. Monday and Tuesday the right lane on southbound US 67 at I-64 will be closed for paving work.
- From 7 p.m. to 5 a.m. nightly through October 18 one lane on northbound and southbound US 67 from Rte. AC to Lynn Haven Ln. will be closed for resurfacing work.
- From 9 a.m. to 3 p.m. Tuesday the right lane on southbound US 67 at I-64 will be closed for paving work.
- The entrance ramps from northbound and southbound US 67 to eastbound and westbound I-64 are closed for paving work. The ramps will be closed until the end of the year.
Rte. 100:
- From 9 a.m. to 3 p.m. Tuesday and Wednesday the right lane on eastbound Rte. 100 from New Ballwin Rd. to Holloway Rd. will be closed for permit work.
Rte. 231:
- From 9 a.m. to 3 p.m. Tuesday and Wednesday one lane on northbound Rte. 231 at Baumgartner Rd. will be closed for permit work.
Rte. BA:
- From 8 a.m. to 7 p.m. daily through November 1 one lane on Rte. BA from Rte. 109 South to Rte. 109 North will be closed for resurfacing work.
Rte. HH:
- From 8 a.m. to 3 p.m. Tuesday through Friday one lane on westbound Rte. HH from Rte. 141 to Baxter Rd. will be closed for construction work.
Rte. JJ:
- The entrance ramp from Rte. JJ to eastbound I-64 is closed for paving work. The ramp will be closed until the end of the year.
Brentwood Blvd.:
- The entrance ramps from Brentwood Blvd. to eastbound and westbound I-64 are closed for paving work. The ramps will be closed until early 2009.
Eager Rd.:
- Access from Eager Rd. to northbound I-170 is closed for paving work. The closure will be in place until early November.
Hanley Rd.:
- The entrance ramps from northbound and southbound Hanley Rd. to westbound I-64 are closed for paving work. The ramps will be closed until late 2009.
I-44 Outer Rd.:
- From 7 p.m. to 7 a.m. Monday through Thursday one lane on eastbound I-44 Outer Rd. from Fox Creek Rd. to Rte. 109 will be closed for resurfacing work.
- One lane on westbound I-44 Outer Rd. from Rte. 109 to Fox Creek Rd. is closed for resurfacing work. The lane restriction will remain in place until Friday.
Laclede Station Rd.:
- The entrance ramp from Laclede Station Rd. to eastbound I-64 is closed for bridge construction work. The ramp will be closed until the end of year.
McCausland Ave.:
- From 7 p.m. to 5 a.m. Monday through Thursday the right lane on southbound McCausland Ave. at Berthold Ave. will be closed for paving work. Access to Berthold Ave. and westbound I-64 will also be closed.
McCutcheon Rd.:
- McCutcheon Rd. at I-64 is closed for bridge construction work. The closure will be in place until the end of the year.
McKnight Rd:
- The entrance ramps from McKnight Rd. to eastbound and westbound I-64 are closed for paving work. The ramps will be closed until the end of the year.
Spoede Rd.:
- Spoede Rd. at I-64 is closed for demolition work. The closure will be in place until the end of the year.
- The entrance ramps from Spoede Rd. to eastbound and westbound I-64 are closed for paving work. The ramps will be closed until the end of the year.
St. Charles County
I-64:
- From 6 p.m. Monday to 6 a.m. Tuesday two lanes on eastbound I-64 at Rte. 94 will be closed for paving work.
Rte. 364:
- From 8 a.m. to 4 p.m. Tuesday through Thursday one lane on westbound Rte. 364 at Arena Pkwy. will be closed for bridge construction work.
Rte. P:
- From 9 a.m. to 4 p.m. Tuesday through Thursday the right lane on westbound Rte. P from Rte. M to Main St. will be closed for permit work.
Prospect Rd.:
- Prospect Rd. is closed at US 40 for bridge construction work. Motorists can access US 40 from Callahan Rd. The closure will be in place until Fall 2009.
Jefferson County
US 61/67:
- From 5 p.m. Monday to 7 a.m. Tuesday one lane on northbound US 61/67 at Richardson Rd. will be closed for paving work.
- From 6 a.m. to 6 p.m. Tuesday the left lane on northbound and southbound US 61/67 from Rte. 110 to Rte. CC will be closed for construction work.
Rte. 21:
- The left lane on northbound Rte. 21 at the Goldman Rd. Spur is closed for bridge construction work. The lane restriction will be in place until December 31.
Rte. P:
- From 9 a.m. to 3 p.m. Tuesday through Friday the right lane on southbound Rte. P at Rte. A will be closed for permit work.
Rte. BB:
- From 8 a.m. to 3 p.m. Monday through Friday through October 15 one lane on Rte. BB from Second St. to Rte. 30 Spur will be closed for construction work.
Franklin County
I-44:
- From 7 a.m. to 8 a.m. Tuesday the right lane on westbound I-44 at Rte. AH will be closed for paving work.
- From 8 a.m. to 9 a.m. Tuesday the right lane on eastbound I-44 from Rte. 30 to Rte. 47 will be closed for paving work.
- From 9 a.m. to 10 a.m. Tuesday the right lane on eastbound I-44 from US 50 to Rte. O will be closed for paving work.
- From 10 a.m. to 11 a.m. Tuesday the right lane on eastbound I-44 from Rte. O to St. Mary's Rd. will be closed for paving work.
Rte. 47:
- From 9 a.m. to 3 p.m. Tuesday through Friday one lane on northbound Rte. 47 from Rte. FF to 3rd St. Pkwy. will be closed for lighting work.
Rte. 100:
- From 7 a.m. to 4 p.m. Tuesday through Friday one lane on eastbound and westbound Rte. 100 from Rte. OO to St. Albans Rd. will be closed for construction work.
- From 8 a.m. to 3 p.m. Monday through Friday through December 31 two lanes on westbound Rte. 100 from Rte. T to Southpoint Rd. will be closed for construction work.